Kanban inventors and implementers are usually very keen on metrics. I, as a Kanban implementer, am no exception. In this article I will share some of my views and ideas on metrics that can be used in Kanban. You must keep in mind that kanban is always about simplicity and focusing on doing just enough to achieve your goals.
Here you can find a non exhaustive, but yet, interesting list of metrics and charts that are very informative and helpful in terms of measuring your team/project performance and evolution.
Here you can find a non exhaustive, but yet, interesting list of metrics and charts that are very informative and helpful in terms of measuring your team/project performance and evolution.
Cumulative Flow Diagram (CFD)
This chart was already described in a previous post. The idea here is to show the distribution of stories per state along the span of a project. The x-axis represents the time and the y-axis shows the number of stories. Each color band represents a column in the board and its height shows the number of cards in that column in a given point in time. The order of the bands should be (from top to bottom) the order that the cards follow in the columns of your board, so the top most band should be “Backlog” and the bottom most should be the “Done”.
With this chart you can extract the following information:
With this chart you can extract the following information:
- Lead time: Indicates the amount of time that a task is in the system. In other words, it measures the time a task takes to get to the “Done” column (deliver a finished task). In a CFD, it can be measured by drawing an horizontal line that connects the top most line and the bottom most line. The length of this horizontal line, in time units, is the lead time.
- Cycle time: It is the same principle as lead time. However, in this case, the idea is to measure the time that a task takes to get from point A to point B in the system. To do this you need to measure the horizontal distance between the two lines that represent points A and B.
- Work in Progress (WIP): Represents the amount of tasks that are in the system. A big WIP tends to increase the lead time, multitasking, stress on the team, etc. It can be measured by a vertical line that connects the bottom most line to the upper most line. The length of this vertical line, in tasks, is the WIP.
- Process bottlenecks: If a sudden increase or reduction in the thickness of any band shows up, it means that there is a bottleneck in that stage of the process. It is a warning sign that should be considered and resolved.
Cycle Time Control Chart
This is a typical Control Chart (a Tool & Technique of the PMI Control Quality process). The x-axis measures the chronological time and the y-axis represents the cycle time of the task. For each task you mark its cycle time on this chart.
The chart should have an horizontal line that represents the mean of the cycle time of all tasks. Then it should have 2 more horizontal lines that are the Upper and Lower Control Limits. These lines are both at the same distance of the average cycle time (one above the average and the other below the average). This distance is, by definition 3 times the standard deviation from the mean. You can follow this rule, but another distance can be defined (and adjusted) by the kanban team or manager. A typical control chart would also have two more horizontal lines called Upper and Lower Specification Limits, but as we don’t have specifications, we won’t consider them.
The idea is to control if the cycle time of the tasks in the system always falls within the control limits. When this is not the case an analysis should be performed and a cause should be identified and corrected in order to prevent it from happen again.
The chart should have an horizontal line that represents the mean of the cycle time of all tasks. Then it should have 2 more horizontal lines that are the Upper and Lower Control Limits. These lines are both at the same distance of the average cycle time (one above the average and the other below the average). This distance is, by definition 3 times the standard deviation from the mean. You can follow this rule, but another distance can be defined (and adjusted) by the kanban team or manager. A typical control chart would also have two more horizontal lines called Upper and Lower Specification Limits, but as we don’t have specifications, we won’t consider them.
The idea is to control if the cycle time of the tasks in the system always falls within the control limits. When this is not the case an analysis should be performed and a cause should be identified and corrected in order to prevent it from happen again.
Lead or Cycle Time Distribution Chart
This chart shows how many tasks took a given amount of time units to get to their destination phase. It enables us to get a visual insight of the likelihood of fulfilling a given task in a certain amount of time.
Flow Efficiency Chart
In an ideal world, 100% of a worker time should be spent on adding value to the product (s)he’s building. However, we all know that this is not true. Heither because (s)he’s waiting for work handoff, or because (s)he’s waiting to another team to fix a bug, or a super priority task showed up and everything else must stop right now, or the specifications aren’t ready yet, or there is an hardware problem, or because the network is down or a provider didn’t fulfill the contract, … You name it. In these situations the time passes and the work doesn’t get done!!!
The Flow Efficiency Chart measures the percentage of time used in a task that was really used for value added purposes. In other words, it is the ratio between the value adding time of a task and its cycle or lead time:
Flow Efficiency[%]=(Value-added Time/Cycle or Lead Time)*100
You can measure this value per task or you can use CFD to provide you the information you require. The first option is the best if you have in place a tool that does these calculations for you, otherwise you will have a hard time doing it. The second option will just provide a mean value per time unit which is a lot easier to calculate (most of the times this is just enough).
The Flow Efficiency Chart measures the percentage of time used in a task that was really used for value added purposes. In other words, it is the ratio between the value adding time of a task and its cycle or lead time:
Flow Efficiency[%]=(Value-added Time/Cycle or Lead Time)*100
You can measure this value per task or you can use CFD to provide you the information you require. The first option is the best if you have in place a tool that does these calculations for you, otherwise you will have a hard time doing it. The second option will just provide a mean value per time unit which is a lot easier to calculate (most of the times this is just enough).
Conclusion
There are much more charts and variances of each described chart, but, in the end of the day, it all comes down to the question: how can I improve my working process? What you need to find is the smallest set of charts/KPIs that provide you the most information about how your work is flowing. These charts/KPIs are the tools that will tell you if the modifications that you should continuously introduce in your process (using the scientific method as described in my previous post), really improved the flow or not. Only with these tools you will really control and improve your workflow.